Saturday 13 September 2014

another milestone

Finally have the plumber, electrician and HVAC contractors all tied down to a start date. early Oct. Roofer is also on board. We are ordering lights and plumbing fixtures. Just a recap on the current schedule. We started in the ground on the last week of July. Framing started 2 1/2 weeks ago and will take another 2 weeks. This includes the installation of the windows. We have been working with only 1 framer and helper as this is the first time I am building this way.  The building is quite complex from a framing perspective. We have been lucky and so far no weather delays. There have been 2 material supply delays. Once the steel beams did not show up. Now I get the steel from another supplier. Another time the floor trusses delayed us 1/2 a day. That error was traced to the general contractor and will not happen again. So far, still targeting an end of November occupancy.

No comments:

Post a Comment