Sunday 26 October 2014

One week later

The roof is complete, the underground hydro trenches, meter base and 4 electrical panels are in and approved. We started installing the rear exit stair and installed the landings. The plumbing and electrical rough in will start this week.


Friday 17 October 2014

Almost have a roof

The roofers were able to finish the 3 small roofs before the monsoon set in for this week. The natural gas has been connected to the building, thank you Aecom, it was a bit struggle to get you there but you came through. The trenches for the hydro have been dug by me in the rain yesterday with the help of a machine (see below). The tree has been trimmed. The weather looks good to finish the main roof next week. We ordered the siding and have contracted the main insulation installer. A couple of exterior windows and doors need to be installed and the interior framing will be done by next Tuesday. The rough ins while start soon. We are now about 2 to 3 weeks behind the schedule I had hoped for, but we are still on budget.