The roofers were able to finish the 3 small roofs before the monsoon set in for this week. The natural gas has been connected to the building, thank you Aecom, it was a bit struggle to get you there but you came through. The trenches for the hydro have been dug by me in the rain yesterday with the help of a machine (see below). The tree has been trimmed. The weather looks good to finish the main roof next week. We ordered the siding and have contracted the main insulation installer. A couple of exterior windows and doors need to be installed and the interior framing will be done by next Tuesday. The rough ins while start soon. We are now about 2 to 3 weeks behind the schedule I had hoped for, but we are still on budget.